Filter Spools Fabrication for Total E&P

Final Hydrotest Chart Result

Members of our Composite Pipe Systems team carried out the fabrication of 6″ GRE pipe coarse filter spools at the GRE Fabrication Facility for EGINA FPSO operated by Total E&P.

The Egina FPSO is the largest ever built by Total. The FPSO is connected to 44 subsea wells 1,600
meters deep and will produce 200,000 barrels of oil per day.

This 8-day project kicked off on August 31st and ended on September 9th.

The fabrication commenced after all materials used were verified and validated by the client’s quality assurance representative. The representative also inspected the entire fabrication process and hydro test activities.

The fabrication commenced after all materials used were verified and validated by the client’s quality assurance representative. The representative also inspected the entire fabrication process and hydro test activities.

Curing process using heating blanket

Personnel at work during the fabrication at BOG Workshop


All Updates


BOG FZE Construction Progresses
Posted on Sunday, April 25, 2021


Milton Roy Side Entry Mixers
Posted on


GRE Repairs On Chevron’s Agbami FPSO
Posted on


GRE Repair and Installation On ERHA FPSO
Posted on


GRE Piping Repair on Etim Platform
Posted on


Installation of HPM Motor Drive At CHI Limited
Posted on


Growth In Nigeria General Industry Sector: What Is Required?
Posted on


BOG Celebrates International Women ‘s Day
Posted on


What I Learnt From BOG’s International Women’s Day Webinar
Posted on


Alliance Classification in the Nigerian Oil & Gas Industry
Posted on Sunday, February 14, 2021


The Human Capacity Dearth in the Nigerian Oil & Gas Industry
Posted on Tuesday, January 5, 2021


Building Resilience in the Workplace In Turbulent Times
Posted on


Construction Commences on BOG’s Multi-Million Dollar Facility
Posted on


Product Focus-Axial Isolation & Control Valves
Posted on


Commissioning Sundyne Gas Compressor at Greenville LNG
Posted on


Fabrication for Total’s Unity FSO
Posted on


IMS Internal Audit
Posted on


Total E&P And Sudelettra Audit/ Inspections for the Ikike GRE Campaign
Posted on Monday, January 4, 2021


WHY YOU SHOULD CHOOSE HAIMO MULTIPHASE METER
Posted on Sunday, November 15, 2020


What You Need to Know About Goodwin Axial Isolation Valves
Posted on Sunday, November 8, 2020


BOG Holds Groundbreaking Ceremony for Multimillion Dollar Facility
Posted on Thursday, October 22, 2020


Changing the Narrative of Nigerian Businesses
Posted on


UF RACK Repair for Total E&P
Posted on


GRE Repair on ERHA FPSO
Posted on Monday, October 19, 2020


GRE Repair on USAN FPSO
Posted on


Filter Spools Fabrication for Total E&P
Posted on


8000 Hours Service of 4units of Ingersoll Rand Rs30i Compressors
Posted on Sunday, October 18, 2020


Commissioning of Sundyne Pump at NLNG
Posted on


The Secrets of Milton Roy’s Success in Africa
Posted on


NCDMB’s Executive Secretary Speech at BOG’s Groundbreaking Ceremony
Posted on