Agbami FPSO Turn Around Maintenance

Chevron’s Agbami FPSO is one of the major crude oil production platforms in Nigeria. It produces about 20 per cent of the country’s daily oil production output. Hence, the turnaround maintenance (TAM) on the platform became necessary to ensure that it continues to produce at optimum capacity, while not completely shutting down the facility. A complete shutdown of the facility would have posed huge challenges for the joint venture partners and the country as a whole.

The objectives of the TAM include:

  • To modify the existing 20” sea water lift pump lines;
  • To install a new flanged 20” x 6” reducing saddle;
  • To install a new flanged 20” x 2” reducing saddle;
  • Effect the repairs of seven (7) broken flanges on the sea water strainer at P3 L2;
  • The fabrication of the 14” CWC overboard line.

Two teams of engineers worked on the project; the day and night crews. The day crew were the first to mobilize to site and were there for a total of twenty-six (26) days prior to the commencement of the TAM. While the second crew (night crew) joined them before the TAM commenced. The project lasted for 47 days. Personnel were mobilized to site on November 7, 2016 and demobilized on December 24, 2016.

BOG field service engineers during the Turn Around Maintenance of Agbami FPSO.

Above and below: Grinding and setting up of the curing process.


All Updates


New Technical Partnership with Raccortubi
Posted on Monday, July 24, 2017


Visit to Mitsui in Dubai
Posted on


Visit to Crosco
Posted on


China Oilfield Services Limited (COSL) Visits BOG
Posted on


Focus on Goodwin
Posted on


Roadshow on Goodwin Axial Isolation and Control Valves
Posted on


Repair of leaking Spoolable GRE Flowline
Posted on


Commissioning of Corrosion Inhibitor Injection Packagedoes
Posted on


BOG Makes Strong Showing at Shell Engineering Week
Posted on


Business Meeting with SPDC Officials
Posted on


Market Strategy Review Session with Ingersoll Rand
Posted on


Sales Training on Instrument Air Compressor
Posted on


Training on Compressors
Posted on


Training of Jointers and Bonders for Egina Project
Posted on


Delivery of OMB Valves to SPDC
Posted on


Shell Q2 2017 Wells Leaders and Contractors CEO Forum
Posted on


Environmental Health Regulatory Compliance Audits
Posted on


Fire Emergency Preparedness Inspection
Posted on


Repair of Sundyne Pump
Posted on


Repair of Milton Roy Dosing Pump
Posted on


2017 Management Retreat and Corporate Strategy Review
Posted on Wednesday, April 19, 2017


BOG Showcases in-country Capabilities at NOGOF 2017
Posted on


Mitsui Visits BOG, Clients
Posted on


BOG Sponsors Lagos International Polo Tournament 2017
Posted on


Agbami FPSO Turn Around Maintenance
Posted on


Training of Jointers and Bonders for Egina Project
Posted on


BOG at HR Expo Africa
Posted on


BOG, Arco collaborate on Operation & Maintenance Services
Posted on


2016 Year End Appraisals
Posted on


Flair Boom Extension Repair on Usan FPSO
Posted on